C_TS412_1909 Dumps PDF 2022 Strategy Your Preparation Efficiently
Latest Verified & Correct SAP C_TS412_1909 Questions
SAP C_TS412_1909 Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books |
|---|---|
| Material > 12% | Explain Work breakdown structure BOM, BOM PS Interface, component assignment in the network, material procurement |
| Reporting < 8% | Determine general reporting requirements and reporting requirements for cost centers. Configure cost center reporting and create report painter reports |
| Project Structures > 12% | Name the components of Work Breakdown Structure, Network and activities, Milestones |
| Cost and Budgets > 12% | Describe procedures for establishing budgets and reporting costs. |
| Revenues and Payments > 12% | Describe the characteristics of Revenues & Payments. |
| Dates > 12% | Describe the importance of various dates which can be tracked for projects |
SAP S/4HANA Project Systems Certification Exam Details:
| Sample Questions | SAP S/4HANA Project Systems Certification Sample Questions |
| Exam Price | $560 (USD) |
| Exam Name | SAP Certified Application Associate - SAP S/4HANA Project Systems |
| Exam Code | C_TS412_1909 |
| Passing Score | C_TS412_1909 - 51% |
| Schedule Exam | SAP Training |
| Duration | 180 mins |
| Reference Books | S4120 (SAP S/4HANA 1909) S4121 (SAP S/4HANA 1909) S4122 (SAP S/4HANA 1909) S4123 (SAP S/4HANA 1909) |
| Level | Associate |
NEW QUESTION 29
You want to allocate overhead rates to a WBS element. What must you assign to the WBS element?
- A. Investment profile
- B. Settlement rule
- C. Costing sheet
- D. Results analysis key
Answer: C
NEW QUESTION 30
What is the reason for assigning billing plans in customer projects?
- A. Billing plans enable the billing process to be carried out.
- B. Billing plans are prerequisites for quotation creation.
- C. Billing plans are copied automatically to the sales order item.
- D. Billing plans are used for revenue planning.
Answer: A
NEW QUESTION 31
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?
- A. Project profile
- B. Data entry profile
- C. Network type
- D. Network profile
Answer: A
NEW QUESTION 32
Where can you assign the user status profile for WBS elements? Note: There are 3 correct Answers to this question.
- A. In the project profile
- B. In the project version
- C. In the project definition of a standard WBS
- D. In the project type
- E. In the operative WBS element
Answer: A,C,E
NEW QUESTION 33
Float time is calculated during scheduling. Which of the following statements about float time are correct? Note: There are 3 correct Answers to this question.
- A. The float time of WBS elements is calculated by extrapolation.
- B. By default, critical activities have a float time, which is less than or equal to zero.
- C. Float time can be negative.
- D. Activities with the time constraint "Must start on" always have a negative float time.
- E. The maximum size of a free float is as large as the total float of an activity.
Answer: B,C,D
NEW QUESTION 34
How can you confirm the working hours of different work centers for a single activity?
- A. Create multiple confirmations for the activity and use the appropriate work center for each confirmation
- B. Enter multiple work centers within a single confirmation
- C. Assign multiple work centers to the activity
- D. Enter direct activity allocation assigning multiple work centers
Answer: A
NEW QUESTION 35
Which objects can be used to specify settlement rules? Note: There are 2 correct answers to this question?
- A. Network header for activity-account-assigned networks
- B. WBS elements
- C. Network activity for activity-account-assigned networks
- D. Standard WBS elements
Answer: B,C
NEW QUESTION 36
Which of the following is used to plan basic dates manually for WBS elements? Choose the correct answers. There are 2 correct answers to this question.
- A. Easy Cost Planning
- B. Project Builder
- C. Schedule Manager
- D. Project planning board
Answer: B,D
NEW QUESTION 37
You have assigned a budget to WBS elements within your project. What function can be used to check assigned values against the current budget?
- A. Easy Cost Planning
- B. Availability control
- C. Cost forecast
- D. Results analysis
Answer: B
NEW QUESTION 38
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However,
the duration did not changed after overall network scheduling. What do you check? Note: There are 2 correct answers to this question
- A. If the maximum reduction level is less than 100
- B. If the reduction strategy is set in each activity
- C. If the appropriate reduction type is set in the parameters for network scheduling
- D. If the reduction strategy is set in the network header
Answer: A,C
NEW QUESTION 39
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?
- A. Hierarchical report on budget updates
- B. Line item report for budgets
- C. Cost element report on budget updates
- D. Structure overview for budgets
Answer: A
NEW QUESTION 40
Project Structures
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project.
What are the prerequisites?
Note: There are 3 correct answers to this question
- A. Standard network with activities
- B. A bill of material with sales views
- C. A production order
- D. Assignment between material and standard network
- E. A material master with sales views
Answer: A,D,E
NEW QUESTION 41
Revenues & Payment
A customer use cross- company - code project with a top billing element and additional billing element underneath (por debajo) for each company code. Although the internal ..
correctly the result analysis summarizes all values to the highest billing element. How can they split the results to the different company codes?
- A. Settle the WBS element to the highest billing element before you do the result analysis.
- B. Split the project intdifferent project according to each company code.
- C. Adjust the customizing of the valuation method in the expert mode of the periodic results analysis accordingly.
- D. Change the project structure so that it correspond better to the company's organization structure.
Answer: D
NEW QUESTION 42
How can you search in the structure overview based on the user status? Note: There are 2 correct Answers to this question.
- A. By searching for the status profile
- B. By searching via status selection profile
- C. By searching for the individual status
- D. By searching via status combination code
Answer: A,C
NEW QUESTION 43
Resources
How can you define external task in your project.
Note : there are 2 correct answers for this question.
- A. Assign a purchase order for external processing to the project definition.
- B. Create an external activity in a network.
- C. Create a service milestone.
- D. Create a service activity in a network.
Answer: B,D
NEW QUESTION 44
In your logistics project you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?
- A. Scheduling and capacity category
- B. Scheduling and distribution key
- C. Capacity planner group in the network header
- D. Control key of an activity
Answer: B
NEW QUESTION 45
What functionality can you perform with activity elements?
- A. Schedule WBS elements
- B. Assign work centers and capacities
- C. Assign material
- D. Create relationships
Answer: D
NEW QUESTION 46
......
C_TS412_1909 PDF Dumps Are Helpful To produce Your Dreams Correct QA's: https://examboost.vce4dumps.com/C_TS412_1909-latest-dumps.html